Heading | 12/13/2021 | CONSTRUCTION METER | Chris Papp | DENIED | | 12/13/2021 7:38:20 AM
1-Install main bonding jumper 250.24(A)(4), equipment enclosures are not permitted to provide continuity between GEC & EGC.
2-Support PVC for trailer feeder per T.352.30
3-Provide expansion fitting for PVC trailer feeder per T.352.44
4-Size over current protection for flexible cords per 240.5 & T.400.5(A)(1)
5-All inverse time circuit breakers are not listed for use with fine stranded conductors such as those in the flexible cord assembly. 110.3(B)
|
|
Heading | 12/14/2021 | CONSTRUCTION METER | Chris Papp | APPROVED | PM PLEASE | 12/14/2021 12:36:01 PM
Close loop
|
|
Heading | 02/17/2022 | UNDERGROUND PLUMB | Steven Ramirez | DENIED | eTRAKiT Inspection Request | 2/15/2022 7:36:19 AM
2/15/2022 7:36 AM PCL CONSTRUCTION SERVICES INC
Contact Name: PCL CONSTRUCTION SERVICES INC
Site Address: 7295 W 56TH AVE
Phone: 3033656500
e-Mail: [email protected]
2/17/2022 8:25:12 AM
Not ready for inspection. Need to expose the DWV system and have a test on it.
|
|
Heading | 02/18/2022 | UNDERGROUND PLUMB | Steven Ramirez | PARTIAL INSPECTION | eTRAKiT Inspection Request | 2/17/2022 1:24:31 PM
2/17/2022 1:24 PM PCL CONSTRUCTION SERVICES INC
Contact Name: PCL CONSTRUCTION SERVICES INC
Site Address: 7295 W 56TH AVE
Phone: 3033656500
e-Mail: [email protected]
2/18/2022 8:14:30 AM
Sections A,B,C,D,E underground PVC plumbing for sanitary drainage, storm drains, and oil/sand interceptor.
|
|
Heading | 03/09/2022 | UNDERGROUND PLUMB | Brad Umbarger | PARTIAL INSPECTION | eTRAKiT Inspection Request | 3/8/2022 3:08:32 PM
3/8/2022 3:08 PM PCL CONSTRUCTION SERVICES INC
Area C UG Plumbing Inspection
Contact Name: PCL CONSTRUCTION SERVICES INC
Site Address: 7295 W 56TH AVE
Phone: 3033656500
e-Mail: [email protected]
3/9/2022 9:04:32 AM
Underground DWV for units and part of dog wash between grid lines H-K and 1-4.
|
|
Heading | 03/16/2022 | UNDERGROUND PLUMB | Steven Ramirez | PARTIAL INSPECTION | 184402 | 3/16/2022 8:09:28 AM
Area C gridline 4-5 J-K
|
|
Heading | 03/21/2022 | UNDERGROUND PLUMB | Steven Ramirez | PARTIAL INSPECTION | 441602 | 3/21/2022 7:46:02 AM
Area C gridline 5-7 H-J
|
|
Heading | 03/31/2022 | UNDERGROUND ELEC | Brad Umbarger | PARTIAL INSPECTION | eTRAKiT Inspection Request | 3/30/2022 4:30:25 PM
3/30/2022 4:30 PM PCL CONSTRUCTION SERVICES INC
Contact Name: PCL CONSTRUCTION SERVICES INC
Site Address: 7295 W 56TH AVE
Phone: 3033656500
e-Mail: [email protected]
3/31/2022 9:40:53 AM
approximately 20 ft. of 4" utility secondary side conduits from S. grade wall to column line 5 (no stub ups into electrical room yet).
|
|
Heading | 04/07/2022 | UNDERGROUND ELEC | Adam Quintana | APPROVED | eTRAKiT Inspection Request | 4/6/2022 12:27:45 PM
4/6/2022 12:27 PM Joshua Cotton
AM
Contact Name: Joshua Cotton
Site Address: 7295 W 56TH AVE
Phone: 7817526666
e-Mail: [email protected]
4/7/2022 3:59:39 PM
Underground from electrical closet east about 100' Abd west about 30'
|
|
Heading | 04/20/2022 | UNDERGROUND ELEC | Brad Umbarger | PARTIAL INSPECTION | eTRAKiT Inspection Request | 4/19/2022 2:31:04 PM
4/19/2022 2:31 PM Joshua Cotton
Contact Name: Joshua Cotton
Site Address: 7295 W 56TH AVE
Phone: 7817526666
e-Mail: [email protected]
4/20/2022 8:44:33 AM
Conduit trench for panel feeders from grid line 5 to 9 (no stub-ups).
|
|
Heading | 04/22/2022 | UNDERGROUND PLUMB | Dan Arvanites | PARTIAL INSPECTION | AM PLEASE | 4/22/2022 10:34:25 AM
4/22/2022. Partial inspection. Sanitary ok from grid line 4- east of 12. In between G and F.
|
|
Heading | 04/28/2022 | UNDERGROUND ELEC | Chris Papp | PARTIAL INSPECTION | eTRAKiT Inspection Request | 4/27/2022 2:51:27 PM
4/27/2022 2:51 PM Joshua Cotton
Contact Name: Joshua Cotton
Site Address: 7295 W 56TH AVE
Phone: 7817526666
e-Mail: [email protected]
|
|
Heading | 05/17/2022 | UNDERGROUND PLUMB | Steven Ramirez | PARTIAL INSPECTION | | 5/17/2022 7:49:06 AM
Storm drainage on the northeast corner of the vault. Sand and oil drainage from the tank to gridline 14.
|
|
Heading | 06/07/2022 | UNDERGROUND PLUMB | Steven Ramirez | PARTIAL INSPECTION | | 6/7/2022 8:02:43 AM
4 inch pvc drain ran to lift station in area D.
|
|
Heading | 06/08/2022 | CEG/UFER | Chris Papp | DENIED | eTRAKiT Inspection Request | 6/7/2022 1:11:17 PM
6/7/2022 1:11 PM Joshua Cotton
Contact Name: Joshua Cotton
Site Address: 7295 W 56TH AVE
Phone: 7817526666
e-Mail: [email protected]
6/8/2022 11:07:54 AM
Footing and foundation are not in direct contact with earth. 250.52(A)(2)
|
|
Heading | 06/27/2022 | UNDERGROUND PLUMB | Steven Ramirez | PARTIAL INSPECTION | SEE NOTES | 6/24/2022 1:30:41 PM
AM PLZ
6/27/2022 7:45:30 AM
Sand and oil drains for gridline 4-7.5 areas B,C,D. From E-H
|
|
Heading | 07/15/2022 | UNDERGROUND PLUMB | Steven Ramirez | PARTIAL INSPECTION | | 7/14/2022 3:12:39 PM
AM PLEASE
7/15/2022 7:37:06 AM
12, 10, and 8 inch storm drains from gridline 4-14.2 E&F
|
|
Heading | 07/21/2022 | UNDERGROUND PLUMB | Steven Ramirez | PARTIAL INSPECTION | | 7/21/2022 7:26:14 AM
Storm drain 16 inch from gridline 4-11.3 in gridline F
|
|
Heading | 08/04/2022 | UNDERGROUND PLUMB | Steven Ramirez | PARTIAL INSPECTION | | 8/4/2022 7:42:50 AM
Vents for the sand/oil interceptor
|
|
Heading | 08/12/2022 | UNDERGROUND PLUMB | Steven Ramirez | PARTIAL INSPECTION | | 8/12/2022 7:40:31 AM
Sewer service line ran on the outlet of the grease trap.
|
|
Heading | 08/19/2022 | UNDERGROUND PLUMB | Steven Ramirez | PARTIAL INSPECTION | | 8/19/2022 7:42:07 AM
Sand and oil drain line for area E gridlines 8-9 and A to E.
|
|
Heading | 08/24/2022 | UNDERGROUND PLUMB | Steven Ramirez | PARTIAL INSPECTION | | 8/24/2022 8:52:34 AM
Storm drains 16 inch pvc gridline 3-14 area B.
|
|
Heading | 09/09/2022 | UNDERGROUND PLUMB | Steven Ramirez | PARTIAL INSPECTION | | 9/9/2022 8:40:42 AM
Sand and oil drainage in area A from gridline 9-15, G-H.
|
|
Heading | 09/21/2022 | UNDERGROUND PLUMB | Frank Goodard | PARTIAL INSPECTION | AM PLEASE | 9/21/2022 9:32:41 AM
1. No approved plans onsite, underground plumbing plans have been approved.
2. No more inspections until approved plans are onsite at time of inspection.
3. Did underground inspection from Column lines 14 to 12, and from grid line G to K. 12 main sewer line.
|
|
Heading | 09/30/2022 | UNDERGROUND PLUMB | Steven Ramirez | PARTIAL INSPECTION | | 9/30/2022 8:39:56 AM
Underground sanitary drainage Area A gridline K-M and 14-15. Highlighted on the city set of plans.
|
|
Heading | 10/14/2022 | UNDERGROUND PLUMB | Steven Ramirez | CANCELLED | A.M. Please | 10/14/2022 8:10:41 AM
Must request the inspections on the correct permit
|
|