Permit No. FND21-00002 Permit Type   FOUNDATION ONLY Site Address   7295 W 56TH AVE
ARVADA, CO 80002-
Applied   02/12/2021 Applicant   TC Denver Development, Inc.
Approved   11/30/2021 Owner   ARVADA URBAN RENEWAL AUTHORITY
Issued   11/30/2021 Contractor   PCL CONSTRUCTION SERVICES INC
Parent Permit No.   COMM21-00029 Description   Fdn Only - Olde Town Residences
  Notes  
 
Date of Inspection Inspection Type Inspector Result Remarks Notes

Heading 12/13/2021CONSTRUCTION METERChris PappDENIED12/13/2021 7:38:20 AM 1-Install main bonding jumper 250.24(A)(4), equipment enclosures are not permitted to provide continuity between GEC & EGC. 2-Support PVC for trailer feeder per T.352.30 3-Provide expansion fitting for PVC trailer feeder per T.352.44 4-Size over current protection for flexible cords per 240.5 & T.400.5(A)(1) 5-All inverse time circuit breakers are not listed for use with fine stranded conductors such as those in the flexible cord assembly. 110.3(B)

Heading 12/14/2021CONSTRUCTION METERChris PappAPPROVEDPM PLEASE12/14/2021 12:36:01 PM Close loop

Heading 02/17/2022UNDERGROUND PLUMBSteven RamirezDENIEDeTRAKiT Inspection Request2/15/2022 7:36:19 AM 2/15/2022 7:36 AM PCL CONSTRUCTION SERVICES INC Contact Name: PCL CONSTRUCTION SERVICES INC Site Address: 7295 W 56TH AVE Phone: 3033656500 e-Mail: [email protected] 2/17/2022 8:25:12 AM Not ready for inspection. Need to expose the DWV system and have a test on it.

Heading 02/18/2022UNDERGROUND PLUMBSteven RamirezPARTIAL INSPECTIONeTRAKiT Inspection Request2/17/2022 1:24:31 PM 2/17/2022 1:24 PM PCL CONSTRUCTION SERVICES INC Contact Name: PCL CONSTRUCTION SERVICES INC Site Address: 7295 W 56TH AVE Phone: 3033656500 e-Mail: [email protected] 2/18/2022 8:14:30 AM Sections A,B,C,D,E underground PVC plumbing for sanitary drainage, storm drains, and oil/sand interceptor.

Heading 03/09/2022UNDERGROUND PLUMBBrad UmbargerPARTIAL INSPECTIONeTRAKiT Inspection Request3/8/2022 3:08:32 PM 3/8/2022 3:08 PM PCL CONSTRUCTION SERVICES INC Area C UG Plumbing Inspection Contact Name: PCL CONSTRUCTION SERVICES INC Site Address: 7295 W 56TH AVE Phone: 3033656500 e-Mail: [email protected] 3/9/2022 9:04:32 AM Underground DWV for units and part of dog wash between grid lines H-K and 1-4.

Heading 03/16/2022UNDERGROUND PLUMBSteven RamirezPARTIAL INSPECTION1844023/16/2022 8:09:28 AM Area C gridline 4-5 J-K

Heading 03/21/2022UNDERGROUND PLUMBSteven RamirezPARTIAL INSPECTION4416023/21/2022 7:46:02 AM Area C gridline 5-7 H-J

Heading 03/31/2022UNDERGROUND ELECBrad UmbargerPARTIAL INSPECTIONeTRAKiT Inspection Request3/30/2022 4:30:25 PM 3/30/2022 4:30 PM PCL CONSTRUCTION SERVICES INC Contact Name: PCL CONSTRUCTION SERVICES INC Site Address: 7295 W 56TH AVE Phone: 3033656500 e-Mail: [email protected] 3/31/2022 9:40:53 AM approximately 20 ft. of 4" utility secondary side conduits from S. grade wall to column line 5 (no stub ups into electrical room yet).

Heading 04/07/2022UNDERGROUND ELECAdam QuintanaAPPROVEDeTRAKiT Inspection Request4/6/2022 12:27:45 PM 4/6/2022 12:27 PM Joshua Cotton AM Contact Name: Joshua Cotton Site Address: 7295 W 56TH AVE Phone: 7817526666 e-Mail: [email protected] 4/7/2022 3:59:39 PM Underground from electrical closet east about 100' Abd west about 30'

Heading 04/20/2022UNDERGROUND ELECBrad UmbargerPARTIAL INSPECTIONeTRAKiT Inspection Request4/19/2022 2:31:04 PM 4/19/2022 2:31 PM Joshua Cotton Contact Name: Joshua Cotton Site Address: 7295 W 56TH AVE Phone: 7817526666 e-Mail: [email protected] 4/20/2022 8:44:33 AM Conduit trench for panel feeders from grid line 5 to 9 (no stub-ups).

Heading 04/22/2022UNDERGROUND PLUMBDan ArvanitesPARTIAL INSPECTIONAM PLEASE4/22/2022 10:34:25 AM 4/22/2022. Partial inspection. Sanitary ok from grid line 4- east of 12. In between G and F.

Heading 04/28/2022UNDERGROUND ELECChris PappPARTIAL INSPECTIONeTRAKiT Inspection Request4/27/2022 2:51:27 PM 4/27/2022 2:51 PM Joshua Cotton Contact Name: Joshua Cotton Site Address: 7295 W 56TH AVE Phone: 7817526666 e-Mail: [email protected]

Heading 05/17/2022UNDERGROUND PLUMBSteven RamirezPARTIAL INSPECTION5/17/2022 7:49:06 AM Storm drainage on the northeast corner of the vault. Sand and oil drainage from the tank to gridline 14.

Heading 06/07/2022UNDERGROUND PLUMBSteven RamirezPARTIAL INSPECTION6/7/2022 8:02:43 AM 4 inch pvc drain ran to lift station in area D.

Heading 06/08/2022CEG/UFERChris PappDENIEDeTRAKiT Inspection Request6/7/2022 1:11:17 PM 6/7/2022 1:11 PM Joshua Cotton Contact Name: Joshua Cotton Site Address: 7295 W 56TH AVE Phone: 7817526666 e-Mail: [email protected] 6/8/2022 11:07:54 AM Footing and foundation are not in direct contact with earth. 250.52(A)(2)

Heading 06/27/2022UNDERGROUND PLUMBSteven RamirezPARTIAL INSPECTIONSEE NOTES6/24/2022 1:30:41 PM AM PLZ 6/27/2022 7:45:30 AM Sand and oil drains for gridline 4-7.5 areas B,C,D. From E-H

Heading 07/15/2022UNDERGROUND PLUMBSteven RamirezPARTIAL INSPECTION7/14/2022 3:12:39 PM AM PLEASE 7/15/2022 7:37:06 AM 12, 10, and 8 inch storm drains from gridline 4-14.2 E&F

Heading 07/21/2022UNDERGROUND PLUMBSteven RamirezPARTIAL INSPECTION7/21/2022 7:26:14 AM Storm drain 16 inch from gridline 4-11.3 in gridline F

Heading 08/04/2022UNDERGROUND PLUMBSteven RamirezPARTIAL INSPECTION8/4/2022 7:42:50 AM Vents for the sand/oil interceptor

Heading 08/12/2022UNDERGROUND PLUMBSteven RamirezPARTIAL INSPECTION8/12/2022 7:40:31 AM Sewer service line ran on the outlet of the grease trap.

Heading 08/19/2022UNDERGROUND PLUMBSteven RamirezPARTIAL INSPECTION8/19/2022 7:42:07 AM Sand and oil drain line for area E gridlines 8-9 and A to E.

Heading 08/24/2022UNDERGROUND PLUMBSteven RamirezPARTIAL INSPECTION8/24/2022 8:52:34 AM Storm drains 16 inch pvc gridline 3-14 area B.

Heading 09/09/2022UNDERGROUND PLUMBSteven RamirezPARTIAL INSPECTION9/9/2022 8:40:42 AM Sand and oil drainage in area A from gridline 9-15, G-H.

Heading 09/21/2022UNDERGROUND PLUMBFrank GoodardPARTIAL INSPECTIONAM PLEASE9/21/2022 9:32:41 AM 1. No approved plans onsite, underground plumbing plans have been approved. 2. No more inspections until approved plans are onsite at time of inspection. 3. Did underground inspection from Column lines 14 to 12, and from grid line G to K. 12 main sewer line.

Heading 09/30/2022UNDERGROUND PLUMBSteven RamirezPARTIAL INSPECTION9/30/2022 8:39:56 AM Underground sanitary drainage Area A gridline K-M and 14-15. Highlighted on the city set of plans.