Online Permit

Permit Number:  COMM24-00027
Permit Address:  7010 GRANDVIEW AVE
Permit Type: COMMERCIAL
Permit Subtype: TENANT FINISH
Job Value: $10,000.00
Description: bathroom installation
Status: CO ISSUED
Applied Date: 2/9/2024
Approved Date: 4/3/2024
Issued Date: 4/4/2024
Permit Contacts
APPLICANT:
Megan Ruder
ARCHITECT:
Fluency- Mackenzie Rattan
CONTRACTOR:
Ruder Construction LLC
ELECTRICAL CONTRACTOR:
LEI COMPANIES INC
ENGINEER:
CMTA- Michael Jurich
MECHANICAL CONTRACTOR:
STANDARD MECHANICAL
OWNER:
Megan Ruder
7010 Grandview Ave Arvada CO 80002
PLUMBING CONTRACTOR:
Elevation Mechanical, Inc.
Fee Summary

Fee Description Fee Amount Amount Paid
table 18-1 $191.75 $191.75
use tax $200.68 $200.68
plan review $124.64 $124.64
electric fee $79.75 $79.75
mechanical fee $49.25 $49.25
plumbing fee $82.80 $82.80

Total $728.87 $728.87

Additional Information

Inspected for Asbestos : AN ASBESTOS INSPECTION HAS BEEN / WAS CONDUCTED ON THE BUILDING MATERIALS THAT WILL BE DISTURBED BY THIS PROJECT. CLEARANCE REPORT MUST BE ONSITE.
Left Side Setback (FT) : 0
Rear Setback (FT) : 0
Elevator Installed : No
Fire Sprinkler Req'd : No
1st Floor Area : 3000
3rd Floor Area : 0
Total Building Area : 3000
Electrical Job Value : 2000
Building Height : 20
Renewable Energy Source :
Mezzanine Area : 0
Use : commerical office sp
If mixed use, list all :
Total Occ. Load : 23
Tap to meter size (in) : 0
Fireline installed : No
Hazardous Materials :
Stand Pipe :
Kitchen Hood Suppression : No
Grease inceptor size :
4th Floor Area : 0
Prin. Front Setback (FT) : 0
Right Side Setback (FT) : 0
Building Footprint Sq Ft : 5200
Fire Alarm Provided : Yes
# of Stories : 2
2nd Floor Area : 0
Basement Area : 0
Mechanical Job Value : 1000
Plumbing Job Value : 2000
Affordable Housing Unit :
6th Floor Area : 0
Dev. Project Number :
Occupancy : B
Type/Construction : Type VB
If Multi-Fam, # of units :
Meter to building size : 0
Sewer Service Size :
High Piled Storage :
Commercial Kitchen : No
Food Prep on Site? : No
Liquor Served : No
5th Floor Area : 0

Permit Information

PERMIT IS NOT VALID UNTIL FEES HAVE BEEN PAID

  1. Every permit issued shall become invalid unless the work on the site authorized by such permit is commenced within 180 days after its issuance, or if the work authorized on the site by such permit is suspended or abandoned for a period of 180 days after the time the work is commenced.
  2. This permit, approved plan sets, and other required documents for this project shall be printed and kept on site until the completion of the project.
  3. Call Before You dig, Call 811 3 working days before the project starts for locations of all utility lines.
  4. Backflow assembly tests must be sent to [email protected].

The issuance of this permit, any inspections made, or certificates of occupancy issue shall not be construed to be a permit for, nor an approval of any violation of Building Codes, Engineering Standards and Specifications, or any other code or ordinance adopted by the City of Arvada. Failure to comply with these laws or correct deficient work shall lead to an immediate revocation of the permit. Per sections 69.0 and 78-309 of the Arvada Municipal Code, the permittee shall be responsible for and bear the sole cost of any required relocation of their facilities located in or adjacent to public rights-of-way whether above or below ground. By accepting this permit, the permittee acknowledges this requirement.

Information you submit to the City of Arvada may be subject to the Colorado Open Public Records Act ("CORA"), C.R.S. ยง24-72-201 et seq. Information you submit via the City's application system will be viewable by the public. As such, do not upload any Personal Identifying Information such as driver's licenses, passports, social security numbers, credit card information, bank account information or dates of birth. The City of Arvada, its officers, employees or agents shall not be liable for damages or losses of any kind arising out of or in connection with the use or performance of information, including but not limited to, damages or losses caused by reliance upon the accuracy or timeliness of any such information, or damages incurred from the viewing, distributing, or copying of those materials.

Approved By: IRO
Approved Date: 4/3/2024