Print Inspection Report

Date Time
10/11/2025
3:14 PM
 
Permit Details
Permit No. DEV22-00036 Permit Type   DEVELOPMENT ROW Site Address   14812 W 69TH AVE
ARVADA, CO 80007-
Applied   11/10/2022 Applicant   Jason P Ganong
Approved   01/03/2023 Owner   ADE LLC
Issued   12/21/2022 Contractor   BVB GENERAL CONTRACTORS - ROW
Parent Permit No.   Description   DA2021-0141 ADE, LLC BLDG - DEV
  Notes  
 
Date of Inspection Inspection Type Inspector Result Remarks Notes

Heading 01/03/2023PRE CONSTRUCTIONFabian RuizAPPROVED9am1/3/2023 12:03:16 PM Pre construction meeting has been completed and development is ready for construction.

Heading 03/31/2023DEV WET UTILITYZach PeacheyAPPROVEDType 13 inlets (2)3/30/2023 2:29:07 PM 3/30/2023 2:29 PM BVB GENERAL CONTRACTORS - ROW Storm inlets rebar Contact Name: BVB GENERAL CONTRACTORS - ROW Site Address: 14812 W 69TH AVE Phone: 9705159866 e-Mail: [email protected] 3/31/2023 4:35:50 PM Two type 13 inlets were formed and poured. All work was done per COA standards

Heading 04/03/2023ROW TRAFFIC**Zach PeacheyAPPROVEDTC MHT4/4/2023 7:51:30 AM Contractors road closure was per MHT plan.

Heading 04/04/2023DEV WET UTILITYZach PeacheyAPPROVED10" hit4/3/2023 2:58:19 PM 4/3/2023 2:58 PM BVB GENERAL CONTRACTORS - ROW digging to expose water line Contact Name: BVB GENERAL CONTRACTORS - ROW Site Address: 14812 W 69TH AVE Phone: 9705159866 e-Mail: [email protected] 4/5/2023 7:37:07 AM Contractor hit an unmarked water service line. Water department came out to shut down the water, a 10" repair clamp was used for temporary fix. All work was done per COA standards.

Heading 04/05/2023DEV WET UTILITYZach PeacheyAPPROVEDTapping4/3/2023 1:08:50 PM 4/3/2023 1:08 PM BVB GENERAL CONTRACTORS - ROW cut in T''s, water tap Contact Name: BVB GENERAL CONTRACTORS - ROW Site Address: 14812 W 69TH AVE Phone: 9705159866 e-Mail: [email protected] 4/5/2023 5:15:38 PM Contractor took out 18LF of 10" AC main and replaced it with 18LF of 10" PVC main. Fireline 6" T was installed on main 1.5 domestic water line was saddle tapped 3/4" irrigation was saddle tapped Contractor upsized 8" main gate valve with 10" because the main is a 10". Hydrant valve was also installed. All work was done per COA standards.

Heading 04/07/2023DEV WET UTILITYRobert GonzalesAPPROVED W/CONDFL/IRR/DL4/5/2023 5:15:44 PM 4/5/2023 5:15 PM BVB GENERAL CONTRACTORS - ROW run fire and irrigation lines Contact Name: BVB GENERAL CONTRACTORS - ROW Site Address: 14812 W 69TH AVE Phone: 9705159866 e-Mail: [email protected] 4/7/2023 7:34:10 AM Contractor stubbed FL/IRR/SL into property, flash filled W 69th Ave Irrigation vault interior plumbing needs to done and Service line meter pit needs to be complete, FL needs to be stubbed into building

Heading 04/07/2023UNDERGRND DETENTION/WATER QUALITYMark ThomasCANCELLEDeTRAKiT Inspection Request4/6/2023 3:06:08 PM 4/6/2023 3:06 PM BVB GENERAL CONTRACTORS - ROW inlet rebar Contact Name: BVB GENERAL CONTRACTORS - ROW Site Address: 14812 W 69TH AVE Phone: 9705159866 e-Mail: [email protected]

Heading 04/10/2023DEV WET UTILITYRobert GonzalesAPPROVEDFire Hydrant Install4/10/2023 7:13:07 AM Contractor installed Fire Hydrant per COA standards.

Heading 04/10/2023ROW ASPHALT**Robert GonzalesAPPROVEDAsphalt Patches4/10/2023 7:11:26 AM A fast Patch completed (2) utility trench patches per COA Standards.

Heading 04/12/2023DEV WET UTILITYZach PeacheyCANCELLEDStop work notice4/11/2023 8:50:56 AM 4/11/2023 8:50 AM BVB GENERAL CONTRACTORS - ROW Contact Name: BVB GENERAL CONTRACTORS - ROW Site Address: 14812 W 69TH AVE Phone: 3036370981 e-Mail: [email protected] 4/13/2023 7:48:42 AM No work was done due to the stop work notice.

Heading 04/18/2023DEV WET UTILITYZach PeacheyAPPROVEDStorm HDPE install4/17/2023 11:24:27 AM 4/17/2023 11:24 AM BVB GENERAL CONTRACTORS - ROW storm pipe Contact Name: BVB GENERAL CONTRACTORS - ROW Site Address: 14812 W 69TH AVE Phone: 3039131930 e-Mail: [email protected] 4/19/2023 7:48:47 AM Contractor started installing 12" HDPE storm. All work was done per COA standards.

Heading 04/19/2023DEV WET UTILITYZach PeacheyCANCELLEDNo flush4/18/2023 3:29:17 PM 4/18/2023 3:29 PM BVB GENERAL CONTRACTORS - ROW Flush and Pressure test of Fire Hydrant Contact Name: BVB GENERAL CONTRACTORS - ROW Site Address: 14812 W 69TH AVE Phone: 3036370981 e-Mail: [email protected] 4/19/2023 11:16:53 AM No flush will be done.

Heading 04/19/2023DEV WET UTILITYZach PeacheyAPPROVEDSanitary service4/18/2023 11:03:13 AM 4/18/2023 11:03 AM BVB GENERAL CONTRACTORS - ROW Sanitary Sewer Install Contact Name: BVB GENERAL CONTRACTORS - ROW Site Address: 14812 W 69TH AVE Phone: 3036370981 e-Mail: [email protected] 4/19/2023 4:22:43 PM Contractor completed the sewer service line up to 5FT outside the foundation. All work was done per COA standards.

Heading 04/20/2023DEV WET UTILITYZach PeacheyAPPROVEDFireline install4/11/2023 12:10:13 PM 4/11/2023 12:10 PM BVB GENERAL CONTRACTORS - ROW Hydrostatic test Fire hydrant Contact Name: BVB GENERAL CONTRACTORS - ROW Site Address: 14812 W 69TH AVE Phone: 3036370981 e-Mail: [email protected] 4/19/2023 2:56:32 PM 4/19/2023 2:56 PM BVB GENERAL CONTRACTORS - ROW waterline install Contact Name: BVB GENERAL CONTRACTORS - ROW Site Address: 14812 W 69TH AVE Phone: 3036370981 e-Mail: [email protected] 4/21/2023 7:36:05 AM Contractor began installing fireline into the DEV. All work was done per COA standards.

Heading 04/21/2023DEV WET UTILITYZach PeacheyAPPROVEDFire line4/20/2023 1:56:24 PM 4/20/2023 1:56 PM BVB GENERAL CONTRACTORS - ROW Water line install Contact Name: BVB GENERAL CONTRACTORS - ROW Site Address: 14812 W 69TH AVE Phone: 3036370981 e-Mail: [email protected] 4/21/2023 5:02:57 PM Contractor installed fire line into foundation. All work was done per COA standards.

Heading 04/24/2023DEV WET UTILITYZach PeacheyAPPROVEDFire line fill4/21/2023 1:43:43 PM 4/21/2023 1:43 PM BVB GENERAL CONTRACTORS - ROW Fill 6" Fire Line 9:00 A.M. Contact Name: BVB GENERAL CONTRACTORS - ROW Site Address: 14812 W 69TH AVE Phone: 3036370981 e-Mail: [email protected] 4/25/2023 7:55:21 AM COA water department filled the fire line for it to stay filled for 24hrs. All work was done per COA standards.

Heading 04/24/2023DEV WET UTILITYZach PeacheyDENIEDPressure test4/21/2023 1:50:11 PM 4/21/2023 1:50 PM BVB GENERAL CONTRACTORS - ROW Bac T test 9:00 am Contact Name: BVB GENERAL CONTRACTORS - ROW Site Address: 14812 W 69TH AVE Phone: 3036370981 e-Mail: [email protected] 4/25/2023 7:56:15 AM Contractor failed fire hydrant pressure test due to loss in PSI.

Heading 04/27/2023DEV WET UTILITYZach PeacheyAPPROVEDFire Line test4/21/2023 1:47:33 PM 4/21/2023 1:47 PM BVB GENERAL CONTRACTORS - ROW flush 6" line 9:00 am and hydrostatic test 12:00 Contact Name: BVB GENERAL CONTRACTORS - ROW Site Address: 14812 W 69TH AVE Phone: 3036370981 e-Mail: [email protected] 4/28/2023 8:07:10 AM Contractor passed their fire line pressure test. Flushing happened after by our Water Department. All work was done per COA standards.

Heading 04/28/2023DEV WET UTILITYZach PeacheyCANCELLEDCancelled4/27/2023 1:24:58 PM 4/27/2023 1:24 PM BVB GENERAL CONTRACTORS - ROW Super flush of 6" fire line, Scheduled with Arvada Fire for 11:00 AM Contact Name: BVB GENERAL CONTRACTORS - ROW Site Address: 14812 W 69TH AVE Phone: 3036370981 e-Mail: [email protected] 4/28/2023 8:15:52 AM Cancelled due to having a schedule miscommunication with Arvada Fire.

Heading 04/28/2023DEV WET UTILITYZach PeacheyAPPROVEDInlets4/27/2023 11:18:48 AM 4/27/2023 11:18 AM BVB GENERAL CONTRACTORS - ROW Storm pipe and inlet construction Contact Name: BVB GENERAL CONTRACTORS - ROW Site Address: 14812 W 69TH AVE Phone: 3036370981 e-Mail: [email protected] 5/1/2023 8:13:40 AM Contractor completed fire hydrant pressure test. Contractor also poured two inlets.

Heading 05/02/2023DEV WET UTILITYZach PeacheyAPPROVEDHDPE install5/1/2023 4:26:46 PM 5/1/2023 4:26 PM BVB GENERAL CONTRACTORS - ROW Storm pipe at outlet Contact Name: BVB GENERAL CONTRACTORS - ROW Site Address: 14812 W 69TH AVE Phone: 3036370981 e-Mail: [email protected] 5/3/2023 8:08:32 AM Contractor installed 10 LF of 12" HDPE. All work was done per COA standards.

Heading 05/04/2023DEV WET UTILITYZach PeacheyAPPROVEDSuper flush4/28/2023 2:37:33 PM 4/28/2023 2:37 PM BVB GENERAL CONTRACTORS - ROW flush/ Super flush wit F.D at11:00 Contact Name: BVB GENERAL CONTRACTORS - ROW Site Address: 14812 W 69TH AVE Phone: 3036370981 e-Mail: [email protected] 5/4/2023 4:59:06 PM Contractor did a super flush with AFD and passed.

Heading 06/09/2023DEV CONCRETEZach PeacheyDENIEDBad subgrade6/8/2023 12:55:27 PM 6/8/2023 12:55 PM BVB GENERAL CONTRACTORS - ROW Pouring crosspan at 3:00 pm Contact Name: BVB GENERAL CONTRACTORS - ROW Site Address: 14812 W 69TH AVE Phone: 3039131930 e-Mail: [email protected] 6/12/2023 8:46:55 AM Contractor installed a new sewer service line. All work was done per COA standards. Contractor installed a new Water service line using a compression fitting. All work was done per COA standards. 6/12/2023 9:02:43 AM Disregard above inspection. Contractor was not ready for concrete cross pan. Subgrade was not proper to place concrete on.

Heading 06/23/2023DEV CONCRETERobert GonzalesAPPROVEDNo Work/weather6/21/2023 11:57:03 AM 6/21/2023 11:57 AM BVB GENERAL CONTRACTORS - ROW Sub grade inspection for entry cross pan Contact Name: BVB GENERAL CONTRACTORS - ROW Site Address: 14812 W 69TH AVE Phone: 3039131930 e-Mail: [email protected] 6/23/2023 7:00:52 AM Contractor cancelled compaction testing due to weather.

Heading 06/26/2023DEV CONCRETEZach PeacheyAPPROVEDSubgrade/prep6/23/2023 9:05:17 AM 6/23/2023 9:05 AM BVB GENERAL CONTRACTORS - ROW sub grade inspection for crosspan Contact Name: BVB GENERAL CONTRACTORS - ROW Site Address: 14812 W 69TH AVE Phone: 3039131930 e-Mail: [email protected] 6/27/2023 8:26:02 AM Contractor subgrade was per COA standards.

Heading 06/27/2023DEV CONCRETEZach PeacheyAPPROVEDConcrete6/26/2023 2:11:54 PM 6/26/2023 2:11 PM BVB GENERAL CONTRACTORS - ROW 9:00 am concrete pour Contact Name: BVB GENERAL CONTRACTORS - ROW Site Address: 14812 W 69TH AVE Phone: 3036370981 e-Mail: [email protected] 6/28/2023 7:48:59 AM Contractor completed concrete. I will create another inspection once I have measured the ADA ramps.

Heading 11/06/2023DEV CONCRETEZach PeacheyAPPROVEDSubgrade test11/3/2023 2:50:20 PM 11/3/2023 2:50 PM BVB GENERAL CONTRACTORS - ROW Subgrade testing for sidewalk Contact Name: BVB GENERAL CONTRACTORS - ROW Site Address: 14812 W 69TH AVE Phone: 3036370981 e-Mail: [email protected] 11/7/2023 7:06:58 AM Concrete subgrade was per COA standards. Passed heal and probe test and compaction testing.

Heading 11/07/2023DEV CONCRETEZach PeacheyAPPROVED16yrds sidewalk11/6/2023 3:07:57 PM 11/6/2023 3:07 PM BVB GENERAL CONTRACTORS - ROW Sidewalk Contact Name: BVB GENERAL CONTRACTORS - ROW Site Address: 14812 W 69TH AVE Phone: 3036370981 e-Mail: [email protected] 11/8/2023 7:49:01 AM Contractor installed 16yards of concrete sidewalk. All work was done per COA standards.

Heading 12/18/2023DEV ASPHALTZach PeacheyAPPROVED24" cut back12/14/2023 8:48:25 AM 12/14/2023 8:48 AM BVB GENERAL CONTRACTORS - ROW remove and replace 2'' asphalt at entry, 10:00 am 1st lift Contact Name: BVB GENERAL CONTRACTORS - ROW Site Address: 14812 W 69TH AVE Phone: 3036370981 e-Mail: [email protected] 12/19/2023 7:11:34 AM Contractor did 3 lifts on the 24" cut back at the entrance. All work was done per COA standards.

Heading 11/14/2024DEV CONCRETEZach PeacheyAPPROVEDDemo11/13/2024 1:05:59 PM 11/13/2024 1:05 PM BVB GENERAL CONTRACTORS - ROW Demo spalling concrete, regrade Contact Name: BVB GENERAL CONTRACTORS - ROW Site Address: 14812 W 69TH AVE Phone: 3039126516 e-Mail: [email protected] 11/14/2024 3:41:48 PM Contractor demoed the concrete cross pan near entrance.

Heading 11/15/2024DEV CONCRETEZach PeacheyAPPROVEDPunch list concrete11/13/2024 3:26:40 PM 11/13/2024 3:26 PM BVB GENERAL CONTRACTORS - ROW 10:00 A.M. Concrete , subgrade Contact Name: BVB GENERAL CONTRACTORS - ROW Site Address: 14812 W 69TH AVE Phone: 3039126516 e-Mail: [email protected] 11/15/2024 4:09:17 PM Contractor completed their punch list item. Concrete cross pan was poured. 4500psi mix, fiber mesh, #4 rebar with epoxy, subgrade passed heel and probe test. All work was done per plan. Ambient temp - 50 degrees. Concrete Blanket - Yes TC - Yes

Heading 01/16/2025DEV WET UTILITYZach PeacheyAPPROVEDTW check1/16/2025 7:44:03 AM Tracer Wire check. 1/16/2025 4:39:17 PM Water department went on site to verify TW works from box. TW does in fact work.

Heading 08/11/2025INITIAL WARRANTYScott GallardoAPPROVEDClean up8/11/2025 9:47:20 AM Initial warranty accepted.