Notes:
2/4/2021 3:41:45 PM
2/8/2021 1:06:19 PM
Email has been sent to Sandra to verify if a grading plan will be needed and to clarify what engineer will be reviewing this permit.
2/17/2021 2:53:45 PM
~Permit: SITE21-00008
~Grading plan: Good
~Erosion Control Plan (BMPs): Good
~ Truck Route Map: Good
~ Stormwater management Plan (SWMP): Good
~ Excavation Contractor: **NEED**
~ Site Contact: **NEED**
~ Custom Screen: Good
~ Engineer review: Jake Sawaya
8/24/2021 4:27:27 PM
Email received from Jennifer Perkins with CEI Eng-
Sam’s Club was not able to secure delivery of the tanks and have moved this project to start in May 2022. Construction complete would likely be in October 2022.
Yes, we are working with the State on the dewatering permit.
8/25/2021 8:27:41 AM
Excavation contractor is still needed.
1/7/2022 2:26:14 PM
Last information per Sandra is they are waiting to proceed until 2022
1/21/2022 4:40:02 PM
Per email from Jennifer Perkins with CEI engineering, this is going out to bid soon.