Notes:
7/16/2024 7:31:57 AM
bore easements in backyards, place 7 new HH and 4 new peds and pull fiber. aerial work and splice fiber
8/8/2024 3:11:28 PM
~Permit: ROW24-00976
~Work to be done: Bore and place
~Location updated: 6800-6859 Pierce St
~Floodplain ?? - no
~ Contractor: Pauley Construction
~ Inspector: Patrick
~Job Value: ok
~ Add Utility Project no to description: ok
~ Review Plans: need additional****
~Is the street 3-5 years old? Or 0-2 years old? 2021 - need letter**** and 2024 paving soon****
~Other Jurisdiction: n/a
~ Sub-Contractor Sign-on’s : ok
~Financial items: Added
~Other Reviews: - need to add***
~Custom Screen: ok
9/3/2024 5:09:25 PM
Under review - RFI 1 - W 68th Ave & Pierce St
9/9/2024 2:46:29 PM
Scott G has given permission to complete work outside of the RFI - will schedule inspections once in approved status
9/24/2024 2:10:32 PM
Under review RFI 2 Plans -
9/27/2024 4:15:47 PM
Under review : RFI 3 - Change Bore Line - W 70th Ave & Kendall St
10/2/2024 11:57:04 AM
While boring near 69th Ave and Jay St:
Marqutel hit a communication line on 9-27-24. That night an emergency crew from (TAK) - sent on behalf of fiber company - was sent out to do temporary repairs. Then, when boring the permanent line, Tak struck an electric line. Tak will need to apply for an emergency permit for all of this work.
Situation caused because locates were done incorrectly.